Good practice preparing for post harvest treatment

The following procedures should be adopted for operation:

  • Mark the tank to show the operating level (full).
  • Add clean water until the tank is approximately three-quarters full.
  • Use a clear area to weigh or dispense chemicals.
  • List chemicals and quantities used in each tank mix.
  • Dilute the concentrate in the ratio of 1 part chemical to 9 parts water. Always cream wettable powders in water before adding to the tank.
  • Add to the tank and fill to the mark. Mix for at least 10 minutes.
  • Label tank clearly with contents.
  • In order to prolong the life of the solution any soil should be removed from the outside of bins to prevent soiling of the yard and of the drenching/dipping solution.
  • Separate the bin reception area from the standing area for treated bins.